- Sergey Nikolaevish Egoshin
- First Deputy of the General Manager — Lead Engineer
We completely understand our responsibilities to the consumers. Both industrial workers and the residents of Tyumen Region, Yugra and Yamala know that Tyumenergo is ready to work in any conditions.
Maintenance Program Implementation
In providing a reliable uninterrupted electricity supply to consumers, it is of high importance that the operating equipment must be maintained in serviceable and good operating condition. Availability for failure free load carrying is achieved by strict compliance with the maintenance terms and regulations, timely diagnostics and determination of maintenance scopes and terms.
According to
Expenses for maintenance of plant and equipment across the Company in
Implementation of the maintenance program for the main electrical equipment of SS and OHL of JSC Tyumenenergo for 2014
mln RUB without VAT
| Name | Own resources method | Contract | Total |
|---|---|---|---|
| Power Line Maintenance | |||
| SS Equipment Maintenance | |||
| Buildings and Structures | |||
| Other Facilities | |||
| Total |
Implementation of the maintenance program on the main electrical equipment at SS and OHL of JSC Tyumenenergo for 2014 , expressed in physical terms
- Maintenance of power transformers
35 –110 kV —54 units; - Maintenance of switches —
264 units; - Maintenance of circuit breakers —
634 units; - Maintenance of
110 kV overhead lines —1372 km; - Maintenance of
35 kV overhead power lines —84 km; - Maintenance of
10 kV overhead power lines —91 km; - Maintenance of
0.4 kV overhead power lines —40 km; - Route clearing —
5892 ha; - Maintenance of
10 /0.4 kV transformer substations —127 units