
- Igor Ivanovich Yaskovets
- Deputy of the General Manager for investment activities
One of the main goals of Tyumenenego investment activities is providing assistance to the regions in implementing industrial potential in accordance with the XMAO strategic development plans for Ugra, YaNao and Tyumen Region.
Investment Activities
Parameters of investment activities
Key figures of implementation of corrected JSC Tyumenenergo” s investment program for
| Application of funds | New fixed assets commissioned | Financing | Capacity Commissioning | Capacity Increase | ||
|---|---|---|---|---|---|---|
| mln RUB, without VAT | mln RUB | mln RUB, with VAT | MVA | km | MVA | km |
Stream and Structure of investment financing
In
Construction of new facilities of power supply network and fixed assets” renovation are directed at sustainable development of the three Russian territories: YanAO, KhMAO and Tyumen Oblast that are included in the Company“s territory.
In the table presented are the major directions of JSC Tyumenenergo investment activities for
| Major directions of capital investments, mln RUB | |
|---|---|
| Investment Program, including | |
| New construction, including: | |
| utility hook-up | |
| Revamping and Re-equipment, including: | |
| utility hook-up | |
| Long-term financial investments | |
| Fixed asset acquisition | |
| For reference only: | |
| utility hook-up |
All revamping and re-equipment work planned for
Implementation of
The most important facilities of
- Construction of distribution network of
0.4 –10 kV power grid for benefit consumers. The result of the construction of distribution network of0.4 –10 kV power grid for benefit consumers for Tyumensky, Tobolsky, Ishimsky and Southern territorial industrial units commissioned are99.720 km and11.924 MVA. - Revamping of Kintus Substation. New fixed assets commissioned —
305.99 mln RUB because of the project realization, power supply reliability has been increased for JSC Sibnefteprovod (Nefteyugansk Trunk Pipeline Directorate), a first category consumer. As a result, reliability of power supply of consumers in maintenance diagrams is increased, and JSC Tyumenenergo” s new image is being formed as a reliable business partner for electric power consumers, thus facilitating carrying on and developing business in the region. - Vostochno-Surgutskaya
110 kV Substation Revamping of35 kV open switchgear, KRUN-6 Package outdoor switchgear new fixed assets commissioned —93.17 mln RUB The substation is situated on the territory of Nefteyugansk Region and is designed for power supply of oil-production facilities of OOO RN-Yuganskneftegaz, a first category consumer. Re-equipment was caused by obsolescence and physical deterioration of the equipment. - Revamping of the Granichnaya
110 kV Substation. New fixed assets commissioned —116.31 mln RUB. New capacity —80 MVA. - Revamp of Yendyrskaya
110 /35 /6kV Substation. New fixed assets commissioned —75.58 mln RUB Realization of the investment project for connection generation from GTPP-48 of OOO Lukoil-Western Siberia will allow ensuring stable work of the station and power systems in standard and emergency modes of operation for the110 kV network. - Elegaz
110 kV110 kV Substation Revamp is in the volume necessary for parallel operation with the power system of gas turbine electric power plant in the area of DNS-3 Station of Eastern-Surgut Deposit. New fixed assets commissioned are130.32 mln RUB. Revamp of the substation was done due to connection of35 kV to the gas turbine electric power plant through 6/35 kV substation via two lines. The result is an increase in reliability of power supply of consumers in Surgutsky Region. - Re-equipment of Relay Protection and Automatic Equipment at Vachinskaya Substation for work with the gas turbine electric power plant. New fixed assets commissioned are
84.77 mln RUB. The result is a35 kV network connection of 6/35 kV (3*16 MVA) step-up substation in the area of DNS-2 Station of the Vachinsky Oil Deposit and36 MW-capacity gas-turbine station of the Vachinsky Oil Deposit. - Revamp of distribution network of
0.4 –10 kV power grid for benefit consumers Activities in re-equipment of distribution networks of the0.4 –10 kV power grid resulted for benefit consumers of Tyumen, Tobolsk, Ishim and Southern territorial industrial units commissioned were35.14 km and7.36 MVA. - Revamping of Metelyovo
110 kV Substation New fixed assets commissioned —24.19 mln RUB. New capacity —10 MVA. - Revamping of the
10 kV Overhead Line in Kugaevo, Tobolsky Region, and Tyumen Oblast. - New fixed assets commissioned are
80.67 mln RUB,53.64 km. of wire was replaced, power balance increase —3.044 km. The result of this project is considerable increase in reliability of power supply to consumers.
Graphic structure of capital investment financing of JSC Tyumenenergo in
Volume of capital investment financing in
In
Results of implementation of investment program in 2014
Implemented activates for lowering specific investment expenditure
Effect from lowering investment expenditures for
Quantity of realised utility hook-up contracts and the volume of realised hook-up contracts (units) including benefit applicantsin 2014 made up 4576 contracts
The total connected capacity was 1,
- Up to
15 kW:4183 contracts were realised with total capacity —0.049796 GW; - From
15 kW up to150 kW:223 contracts were realised with total capacity —0.013009 GW.
Level of Electric Power Losses
Dynamics of power losses in absolute and relative amount in
JSC Tyumenenergo is implementing the developed Program of Energy Saving and Power Efficiency Increase (further — Program). As a result of implementation of Program activities, in JSC Tyumenenergo” s grid in
- as a result of administrative procedures losses decreased by
15.7 m. kilowatt-hour for the total sum36.2 mln RUB; - as a result of programs of prospective development of metering systems for retail power energy of JSC Tyumenenergo — losses decreased by
9.6 mln kilowatt-hour for the total sum25.6 mln RUB; - because of revamping and re-equipment programs — losses decreased by
26.8 mln kilowatt-hour for the total sum44.6 mln RUB
Capacity utilization and increase,
in number of open main substations (S load/S un)
Deterioration level of fixed assets
Deterioration level of fixed assets in
Share of equipment with above-limit service life
Emergency rate
In
Long-term Investment Program
Company“s Investment Program for
Investment Program for
The planned value of financing of investment program of JSC Tyumenenergo for
Volume of financing for 2014 –2019 , mln RUB with VAT
Volume of investment for 2014 –2019 , mln RUB
Volume of fixed assets commissioning
for 2014 –2019 , mln RUB
For
For
For